Lafayette Downtown Congestion Reduction Plan

Lafayette Downtown Congestion Reduction Plan

Lafayette

Downtown Congestion Reduction Plan

Project Summary
Begun in 2015, the purpose of the Lafayette Downtown Congestion Reduction Plan was to formulate policies and projects to address traffic congestion issues in Downtown Lafayette. These issues were previously identified as part of a focused study that preceded the Plan.

As the Transportation Planner for the City, I led this planning effort, serving as primary point of contact and project manager. To help develop this plan the City also retained primary consultant, Arup, a world-renowned architecture, engineering, and design firm.

Project Summary
Begun in 2015, the purpose of the Lafayette Downtown Congestion Reduction Plan was to formulate policies and projects to address traffic congestion issues in Downtown Lafayette. These issues were previously identified as part of a focused study that preceded the Plan.

As the Transportation Planner for the City, I led this planning effort, serving as primary point of contact and project manager. To help develop this plan the City also retained primary consultant, Arup, a world-renowned architecture, engineering, and design firm.

Role
Lead transportation planner & project manager

Role
Lead transportation planner & project manager

Timeline
2015 - 2018

Timeline
2015 - 2018

Stakeholders
20,000+ Lafayette residents, businesses, & visitors
Downtown Congestion Reduction Plan Steering Committee
Lafayette Circulation Commission
Lafayette City Council
Lafayette Unified School District

Stakeholders
20,000+ Lafayette residents, businesses, & visitors
Downtown Congestion Reduction Plan Steering Committee
Lafayette Circulation Commission
Lafayette City Council
Lafayette Unified School District

Project Value
$500,000 planning & design contract
$10 million+ implementation program

Project Value
$500,000 planning & design contract
$10 million+ implementation program

Key Outcomes & Insights

Over $10 million in project solution ideas

Over $10 million in project solution ideas

Over $10 million in project solution ideas

Through dozens of Steering Committee meetings, public workshops with citizen stakeholders, and City Council review, we achieved approval for an implementation program worth over $10 million to considerably improve mobility in Downtown Lafayette.

The most cost-effective solutions increase roadway capacity with more efficient uses of existing roadway space

The most cost-effective solutions increase roadway capacity with more efficient uses of existing roadway space

The most cost-effective solutions increase roadway capacity with more efficient uses of existing roadway space

While some long-term solutions could include major infrastructure redevelopment, extensive planning analysis indicated reallocating existing traffic lanes to multimodal uses could yield the greatest impact in the (relatively) quickest timeframe.